Determine the order point


Question:

Aztec Company expects daily usage of 500 pounds of material Inca, an anticipated lead time of seven days, and a desired safety stock of 2,500 pounds.

a. Determine the order point.

b. Determine the number of pounds to be issued from safety stock if the new order is four days late.