Determine separate resource loadings for systems analysts


Assignment:

The requirements for systems analysts and programmers for the GUMBY project are as follows:

Activity                            J       M     V    Y    L    Q      Z

Predecessors                      -      J     M    V    J     L     Y,Q
Duration (weeks)                6      4     6     8    2    8      2
Systems Analysts (weekly)   8      8     5     3    2    5      3    
Programmers (weekly)          3      4     2     3    3    2      3

a. Compute ESs, LSs, and total slack times.

b. Then show the separate resource loadings for systems analysts and programmers, assuming early start times.

c. Suppose the maximum weekly availability is eight systems analysts and five programmers. Can activities be scheduled to satisfy these constraints without delaying the project?

Solution Preview :

Prepared by a verified Expert
Operation Management: Determine separate resource loadings for systems analysts
Reference No:- TGS02960232

Now Priced at $30 (50% Discount)

Recommended (90%)

Rated (4.3/5)