Describe how expected activity times and variances can be


Question

PERT networks use a simple statistical method to determine the most likely task completion times. Describe how expected activity times and variances can be computed in a PERT network.

Describe a situation in which a project manager would choose PERT for her project.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Describe how expected activity times and variances can be
Reference No:- TGS02691720

Expected delivery within 24 Hours