Consider following table:

  PRET. ACT TIME         ESTIMATES          (days)
Activity   to   tml   tp   te
A - 6 6 6  
B A 4 5 6  
C A 2 4 6  
D B 4 6 8  
E C 1 3 5  
F D 1 5 3  

 Make a PERT network. Draw as shown in notes.