Complete the project ahead schedule


Using the solution from Problem 5 and given the list of crash times and costs, determine the new diagram and times.

Assume for every day you complete the project ahead schedule you recieve a $60 bonus payment.

Question 5 Solution:

Critical Path = ABDFG Total Project Time = 42

PERT Time
11
8
6
8
10
4
11


Total Cost


Maximum
Activity Normal Crash Normal Crash Reduction
A 11 4 150 550 7
B 8 3 300 450 5
C 6 6 600 750 0
D 8 4 100 100 4
E 10 5 650 680 5
F 4 1 750 945 3
G 11 2 225 300 9

Total Crash Costs =

New Crashed Project Time =

Request for Solution File

Ask an Expert for Answer!!
Basic Statistics: Complete the project ahead schedule
Reference No:- TGS0744099

Expected delivery within 24 Hours