Basic Estimating Problem:

Your company is installing a new piece of machining equipment and a robotic arm. Your manager asks for the project costs by cost category as well as the total amount. Given the following information, develop a base cost estimate by grouping costs by Equipment / Material (items 1 - 4), Installation / Labor (items 5 and 6), and Overhead (items 7-9).

1. Two pieces of equipment costing $ 15,000 and $ 35,000

2. Material required for electrical hook-up is 400 feet at $ 25 per foot

3. Controls for each piece of equipment are estimated at $ 600 each

4. Required start-up material is 3,700 pounds at $ 2.70 per pound

5. Company labor for installation requires two maintenance specialists for two days at eight hours per day and $ 35 per hour

6. Contract labor is estimated at a fixed price of $ 7,500

7. Engineering is estimated to be 15% of (equipment / material) cost based on past experience

8. Inspection is estimated to be 3% of (labor) cost based on past experience

9. General and Administrative expenses are estimated to be 5% of the total of (equipment / material) and (labor) based on past experience.