As a production manager, you have received an order for product A that needs two subassemblies and two units of component B. The order is for 1000 units of Product A.

The first subassembly consists of a frame, two supports, and a handle. The second subassembly consists of a hub and five blades.

The following table gives lead times, on-hand inventory, and scheduled receipts.

a) Construct a product structure.

b) Construct a time-phased product structure

c) Prepare a net material requirements plan