A public accounting firm requires the following activities


Question: 1. A public accounting firm requires the following activities for an audit:

145_IP.png

a. Draw a network for this project.

b. Make a forward pass and a backward pass to determine ES, LS, EF, and LF.

c. What are the critical path and the project completion time?

d. If the project completion must be reduced by two days, which activities might be affected?

2. The following activities are required in starting up a new plant:

1890_IP 1.png

a. Draw a network for this project.

b. Make a forward and backward pass to determine ES, LS, EF, and LF.

c. Calculate slack.

d. Prepare a Gantt chart for this project.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A public accounting firm requires the following activities
Reference No:- TGS02705232

Expected delivery within 24 Hours