a) High head power plant – When the water level exceeds the height of the 70m , the hydroelectric power plant is said to be high head power plant. The Pelt on wheel turbine is used as the prime mover.
b) Medium head power plant – When the height of head water ranges between 15m to 70m, then the hydroelectric power plant is called as medium head power plant. Francis turbine is used as the prime mover.
c) Low head power plant – When the height of the head of water is less than 15m, then the hydro electric power plant is called as low head power plant. Kaplan turbine is used as the prime mover.
Mention four thermodynamic processes which are involved in the Diesel Cycle.
Factors influencing the selection on pile.
Whether sheets or geo-grids can replace reinforcing elements in soil nails?
Main purpose of gap in the road on bridge: The main purpose of the gap in the road is to permit the road to expand and contract with temperature modifications without causing harm or deformation to road.
What are the reasons to use Pile foundations during construction?
Define the term Isothermal Efficiency of Air Compressor.
Write a short note on Priming.
Students form a group and then choose 10 ha area for designing. The subdivision chosen must be a vacant land which needs to be developed and must be located within Australia. Students are required to use Micro station , MX Road , Google Earth and CIRCLY design software to complete the project. The p
Answer the given questions. The slab shown below forms a walkway between buildings in a new hospital complex.
Define: a) Fore bearing. b) Back bearing.
18,76,764
1930161 Asked
3,689
Active Tutors
1430660
Questions Answered
Start Excelling in your courses, Ask an Expert and get answers for your homework and assignments!!