Ketchem All Detective Agency is evaluating its system. The company gathered the information below:

  Process

Available
Hours per
Week

Value-Adding
Time (hours
per client)

Average
Demand

  Interviews

69       

13       

20       

  Research

131       

14       

31       

  Pursuit

75       

4.50       

136       

  Travel

200       

14       

61       

Practical capacity is 80% for each process.

1. Which process is most likely to be a current bottleneck?