What was the direct materials flexible budget variance


For 2013, X Company estimated production of 3,500 units of finished product and direct material cost of $23,730. Actual production in 2013 was 2,900 units of finished product, and actual direct material cost was $14,520. What was the direct materials flexible budget variance in 2013 (assume that a positive number means a favorable variance and a negative means an unfavorable variance)?