What is the theoretical fixed manufacturing overhead rate


Question: 1. Soul Socket Inc. manufactures socket wrenches.

-For next month, the vice president of production plans on producing 4,450 wrenches per day.

-The company can produce as many as 5,000 wrenches per day, but is more likely to produce 4,500 per day.

-The demand for wrenches for the next three years is expected to average 4,250 wrenches per day.

-Fixed manufacturing costs per month total $374,000.

-The company works 22 days a month.

-Fixed manufacturing overhead is charged on a per-wrench basis.

Required: a. What is the theoretical fixed manufacturing overhead rate per wrench for the next month?

b. What is the practical fixed manufacturing overhead rate per wrench for the next month?

c. What is the normal fixed manufacturing overhead rate per wrench for the next month?

d. What is the master-budget fixed manufacturing overhead rate per wrench for the next month?

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: What is the theoretical fixed manufacturing overhead rate
Reference No:- TGS02679737

Expected delivery within 24 Hours