Q: A process makes two products, A and B. and operates 5 days per week, 8 hours per day. Demand for the two products for the next week is as follows: What is the takt time of the process? What would a level production schedule look like?

Day 1: A:20  B:26
Day 2: A:10  B:15
Day 3: A:20  B:19
Day 4: A:18  B:20
Day 5: A:12  B:20