What is the projects expected net present value


Problem:

Oklahoma Instruments

Oklahoma Instruments (OI) is considering a project that has an up-front cost of $250,000. The project's subsequent cash flows critically depend on whether its products become the industry standard. There is a 50 percent chance that the products will become the industry standard, in which case the project's expected cash flows will be $110,000 at the end of each of the next five years. There is a 50 percent chance that the products will not become the industry standard, in which case the project's expected cash flows will be $25,000 at the end of each of the next five years. Assume that the cost of capital is 12 percent.

Refer to Oklahoma Instruments. Based on this information, what is the project's expected net present value?

Solution Preview :

Prepared by a verified Expert
Finance Basics: What is the projects expected net present value
Reference No:- TGS02045116