What is the overhead variance and is it overapplied


Jones Company applies overhead based on direct labor hours. At the beginning of the year, Jones estimates Overhead to be $480,000, Machine Hours to be 120,000, and Direct Labor to be 80,000. During January, Jones has 6,700 direct labor hours and 11,000 machine hours. If the actual overhead for January is $41,000, what is the overhead variance and is it overapplied or underapplied? Answer $800 underapplied $800 overapplied $3,000 underapplied $3,000 overapplied none of these.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: What is the overhead variance and is it overapplied
Reference No:- TGS0672235