What is the fixed overhead spending variance


Burnet Company has budgeted fixed overhead of $150,000 based on budgeted production of 5,000 units. During October, 4,800 units were produced and $157,600 was spent on fixed overhead. What is the fixed overhead spending variance?

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: What is the fixed overhead spending variance
Reference No:- TGS0684339