What is the expected time for each activity


Assignment: Project Management

Consider a project having the following seven activities, and address the following questions:

Optimistic Most likely Pessimistic

Immediate Time Time Time

Activity Predecessors (weeks) (weeks) (weeks)

A none 2 3 4

B A 4 4 8

C A 3 5 7

D B 5 5 5

E B, C 3 6 7

F D 4 5 9

G E, F 3 3 7

(a) What is the expected time for each activity?

(b) What is the expected project completion time?

(c) What is the critical path?

(d) What is the variance for each activity?

(e) What are the expected time and variance of each path?

(f) What is the probability that the project will be completed in less than 24 weeks?

Format your assignment according to the following formatting requirements:

1. The answer should be typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.

2. The response also includes a cover page containing the title of the assignment, the student's name, the course title, and the date. The cover page is not included in the required page length.

3. Also include a reference page. The Citations and references should follow APA format. The reference page is not included in the required page length.

Solution Preview :

Prepared by a verified Expert
Project Management: What is the expected time for each activity
Reference No:- TGS02984686

Now Priced at $20 (50% Discount)

Recommended (94%)

Rated (4.6/5)