What is the average tardiness


The following jobs are waiting to be processed at Rick Solans machine center. Solans machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day) compute all times based on initiating work on day 241

Job

Date received

Due date

Duration (days)

1

235

360

40

2

231

310

30

3

228

300

15

4

225

270

25

5

230

320

35

What is the average tardiness (job lateness) for the sequence using the FCFS rule?

The sequence is

Job

4

3

5

2

1