We are evaluating a project that costs 831000 has an


We are evaluating a project that costs $831,000, has an nine-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 100,000 units per year. Price per unit is $37, variable cost per unit is $21, and fixed costs are $832,662 per year. The tax rate is 33 percent, and we require a 14 percent return on this project. The projections given for price, quantity, variable costs, and fixed costs are all accurate to within +/- 20 percent.

Calculate the Best and worst case NPV.

Request for Solution File

Ask an Expert for Answer!!
Financial Management: We are evaluating a project that costs 831000 has an
Reference No:- TGS02699678

Expected delivery within 24 Hours