Using the percentage-of-completion method


Shanahan Construction Company has entered into a contract beginning January 1, 2012, to build a parking complex. It has been estimated that the complex will cost $600,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $900,000. The following data pertain to the construction period.



2012
2013
2014
Costs to date
$270,000
$450,000
$610,000
Estimated costs to complete
330,000
150,000
-0-
Progress billings to date
270,000
550,000
900,000
Cash collected to date
240,000
500,000
900,000


(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.

Gross profit recognized in 2012
$
Gross profit recognized in 2013
$
Gross profit recognized in 2014
$


(b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period.

Gross profit recognized in 2012
$
Gross profit recognized in 2013
$
Gross profit recognized in 2014
$

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Using the percentage-of-completion method
Reference No:- TGS0696721

Expected delivery within 24 Hours