Use appropriate nodes and arrows to draw the network


A Project consists of the following activities. Activities Times are given in weeks.

Activity

Immediate Predecessors

Optimistic

Most Likely

Pessimistic

A

--

13

14

17

B

A

14

16

20

C

A

15

18

20

D

A

3

11

12

E

B

12

15

16

F

B

15

18

20

G

C, F

25

28

31

H

D

12

15

19

I

H

16

18

22

J

G, I

6

8

11

K

E, J

13

15

21

Use appropriate nodes and arrows to draw the network diagram. On the network diagram, label the activity time under each node.