The required rate of return is 12 for projects at this


Suppose a company has two mutually exclusive projects, both of which are three years in length. Project A has an initial outlay of $9,000 and has expected cash flows of $3,000 in year 1, $3,000 in year 2, and $4,000 in year 3. Project B has an initial outlay of $10,000 and has expected cash flows of $2,000 in year 1, $4,000 in year 2, and $5,000 in year 3. The required rate of return is 12% for projects at this company. What is the net present value for the best project? (Answer to the nearest dollar.)

Request for Solution File

Ask an Expert for Answer!!
Financial Management: The required rate of return is 12 for projects at this
Reference No:- TGS02811765

Expected delivery within 24 Hours