Question:

Preparing a standard cost summary and making journal entries

The normal capacity of Austin Adhesives, Inc., is 40,000 direct labor hours and 20,000 units per month. A finished unit requires 6 pounds of materials at an estimated cost of $2 per pound. The estimated cost of labor is $10.00 per hour. The plant estimates that overhead for a month will be $40,000. During the month of March, the plant totaled 34,800 direct labor hours at an average rate of $9.50 an hour. The plant produced 18,000 units, using 105,000 pounds of materials at a cost of $2.04 per pound.

1. Prepare a standard cost summary showing the standard unit cost.

2. Make journal entries to charge materials and labor to Work in Process.