A job order cost sheet for Lowry Company is shown below.

Job No. 92



For 2,000 Units

Date

Direct 
Materials

Direct 
Labor

Manufacturing 
Overhead

Beg. bal. Jan. 1

5,000

6000

5100

8

6,000



12


8000

6400

25

2,000



27


4000

3200


13000

18000

14700





Cost of completed job:




Direct materials



$13,000

Direct labor



18,000

Manufacturing overhead



14,700

Total cost



$45,700

Unit cost ($45,700 2,000)



$22.85

(a) On the basis of the foregoing data, answer the following questions.

(1) What was the balance in Work in Process Inventory on January 1 if this was the only unfinished job?

(2) If manufacturing overhead is applied on the basis of direct labor cost, what overhead rate was used in each year?

(b) Prepare summary entries at January 31 to record the current year's transactions pertaining to Job No. 92.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Prepare summary entries at january 31 to record transactions
Reference No:- TGS02037389

Now Priced at $20 (50% Discount)

Recommended (97%)

Rated (4.9/5)