Prepare a master schedule given this information the


Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 30 units. The production run size is 40 units.

The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Then calculate the units that are available to promise.

Customer orders are follows:

WEEK

Customer Order

1        32
2        15
3         6
4         0

Show ALL work