Precision machinery has set standard times for its field


Precision Machinery has set standard times for its field representatives to perform certain jobs. The standard time allowed for routine maintenance is 0.8 hours? (i.e., "standard output"equals=1.25 jobs per? hour).

One of? Precision's field representatives records the results below.

Calculate the? rep's efficiency for each customer and her average efficiency.

Calculate the? rep's efficiency for each customer. Fill in the table below ?(enter your responses rounded to one decimal? place).

Customer             Actual time required to perform routine maintenance, hours
ABC Company           1.4
Preztel                    0.7
SCR Industries          1.1
BeetleBob                0.8