In a material requirements plan (MRP) the order release date is calculated by:

a - adding ordering lead time to the project date of material shortage

b - determining project date of material shortage by backing up by the order lead time period.

c - adding the ordering lead time to the finished goods delivery date called for in the master scheduled

d - adding demand during lead time to safety stock

I believe the answer is B not completely sure