network diagram and identify all the pathgiven


Network diagram and identify all the path

Given the information in the following table

Activity Duration Predecessor
a 4 None
b 6 a
c 4 a
d 2 c
e 4 b
f 5 b, d
g 3 c
h 4 f,g
i 2 e, h

a. Construct the network diagram

b. Identify each activity's EST, EFT, LST adn LFT

c. Identify all paths. Which path is the critical path?

d. Calculate the slack each activity?

e. How long will it take to complete the project?