Indicate the correct net requirements planned order


Problem

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. 


WEEK NUMBER

ITEM J 0 1 2 3 4 5
Gross requirements

70
46 69
On hand 36




Net requirements





Planned order receipt





Planned order release







Period 1 2 3 4 5
Item J
LT = 1
Q = L4L
Gross requirements
70
46 69
Scheduled receipts




Projected available balance




Net requirements




Planned order receipts




Planned order releases



 