1. A fast-food trainee takes an hour to prepare his first 20 sandwiches, 45 minutes for the second 20, and 38 minutes for the third 20. What will his production rate be after 24 hours of experience?

2. A new bank clerk needed an hour to encode his first 500 checks, 51 minutes for the second 500, and 46 minutes for the third 500. After how many batches of 500 checks will he be able to work at the standard rate of 1,000 checks per hour?