Plainwell Polymers is going to producing the main dashboard structure for a new car design. The dashboard will be produced in three colors with expected daily demand as follows: Black: 390 units/day Grey: 170 units/day Tan: 160 units/day The injection-molding machine can produce a total of 965 parts per day running 24 hours per day.

If Plainwell going to produce the parts using a cyclic schedule and it takes 2 hours change from one color is to the next, what is the minimum cycle time for the cycle schedule in hours?