Identify the original finish date for the entire project


Assignment:

This exercise begins with information for a building project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors, add resources, and make changes to the original plan. Each student is required to submit their own, unique Project file.

A. Enter the following tasks, including the specified duration, specified predecessors, and specified resources. Tasks that are bolded are summary tasks and the indented tasks are sub-tasks. HW7 Tasks FilePreview the document. Make the Start date of the project: June 1st, 2018.

B. Identify the Original Finish Date for the entire project. Save the baseline for the project. Be sure the project has been set to automatically scheduled.

C. You now have received the following update from the field:

Items 1-20 completed on time.

Item 21 delayed as inspector was on vacation causing a 5-day delay, but now is complete.

Item 24 Wallboard is 40% complete

Item 25 Stairway is 80% complete

Item 26 Since the painting contractor could not start on time he has now informed you that he has started another job and you will have to wait until it is done. The new date he will be available to start is October 1st, 2018.

Item 28 the landscape crew says the raised garden material will not arrive on time and he is not able to start until September 19th, 2018.
Input the above data into project (do not change the baseline plan). Annotate reasons for schedule changes (e.g., inspector delay, painting). (Use the notes feature)

D. The customer wants to know if the walk-through date and final project completion date is on schedule. Is it? If not what are the dates?

E. The boss just called and said that the delay is unacceptable to the customer. What can you change to make the project finish on time? Remember to give good justification for the changes.

For your written response to B, D and E, submit a Word document using complete sentences. Remember to make your changes in response to E in the project to get the project to align with the original final completion date.

Attachment:- Tasks list.rar

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Identify the original finish date for the entire project
Reference No:- TGS02799219

Expected delivery within 24 Hours