How long should the project take from start to finish what


1. In publishing a textbook, the following simplified sequence of activities applies, as shown below:

1923_Simplified sequence.jpg

a) Construct the (PERT/CPM) network representation for this PROJECT.  (This problem may also be easier if done with paper and pencil rather than Excel.)

(i) How long should the project take from start to finish? 

(ii) What activities are on the critical path

b) If the project is well managed, it is possible to produce a book in 20 months or less without crashing any activities.  This seems to contradict the findings in "a".  (Please give short answers to this question.)

(i) How do you think publishers get the job done so quickly?

(ii) Is PERT/CPM applicable to publishing?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: How long should the project take from start to finish what
Reference No:- TGS02793329

Expected delivery within 24 Hours