Find the all-normal schedule and cost


Problem 1: The following data were obtained from a study of the times required to conduct a consumer test panel study:

 

Crash Schedule

Normal Schedule

Activity

Time

Cost

Time

Cost

1-2

3

$6

5

$4

1-3

1

$5

5

$3

2-4

5

$7

10

$4

3-4

2

$6

7

$4

2-6

2

$5

6

$3

4-6

5

$9

11

$6

4-5

4

$6

6

$3

6-7

1

$4

5

$2

5-7

1

$5

4

$2

Note: Costs are given in thousands of dollars, time in weeks

(a) Find the all-normal schedule and cost.
(b) Find the all-crash schedule and cost.
(c) Find the total cost required to expedite all activities from all-normal (see a) to all-crash (see b).
(d) Find the least-cost plan for the all-crash time schedule.  Start from the all-crash problem (see b).  Assume partial crashing.

Problem 2: The network for shooting a TV commercial as shown in the table has a fixed cost of $90 per day, but money can be saved by shortening the project duration.  Find the least-cost schedule.

 

Normal

Crash

Cost Increase

Activity

Time

Time

(1st, 2nd, 3rd day)

1-2

7

4

$30, $50, $70

2-3

9

6

$40, $45, $65

1-3

12

10

$60, $60

2-4

11

9

$35, $60

3-4

3

3

-


Cost/Schedule Control System Criteria

1. Calculate cost schedule and variance.

2. Interpret the cost and schedule status of case 3, 10, 11, and 12.

Case

BCWS

ACWP

BCWP

Cost Variance

Schedule Variance

1

800

800

800

 

 

2

800

600

400

 

 

3

800

400

600

 

 

4

800

600

600

 

 

5

800

800

600

 

 

6

800

800

     1000

 

 

7

800

     1000

     1000

 

 

S

800

600

800

 

 

9

800

     1000

800

 

 

10

800

     1000

600

 

 

11

800

600

     1000

 

 

12

800

1200

     1000

 

 

13

800

     1100

1200

 

 

Note: Cost variance = BCWP – ACWP (negative values = overruns)

Schedule variance = BCWP – BCWS (negative values = slippage)

Imhotep, project manager for building a pyramid, is asked by the Pharaoh: "How much of the pyramid is completed?" Imhotep knows that the pyramid will use 1 million stone blocks. He also knows that 700,000 blocks have been used to date. He tells the Pharaoh that the pyramid is 70 percent complete. What is the problem with this assessment?

Solution Preview :

Prepared by a verified Expert
Project Management: Find the all-normal schedule and cost