Expected completion time of the project


Joe used a project management software package and has determined the following results for a given project. Expected completion time of the project = 22 days Variance of project Completion time = 2.77. What is the probability of completing the project over 20 days?

0.3849

0.8849

0.1151

0.7642

0.2358