Evaluating projects with risks


Problem:

The capital budgeting manager of Conscientious Construction Company (CCC) submitted the following report to the CFO:

Project IRR Risk
A 9.0% Low
B 10.0 Average
C 12.0 High

CCC generally takes risk into consideration by adjusting its average required rate of return (r), which equals 8 percent, when evaluating projects with risks that are either substantially lower or substantially higher than average. A 5 percent adjustment is made for high-risk projects, and a 2 percent adjustment is made for low-risk projects. If the above projects are independent, which project(s) should CCC purchase?

Solution Preview :

Prepared by a verified Expert
Finance Basics: Evaluating projects with risks
Reference No:- TGS02047802

Now Priced at $20 (50% Discount)

Recommended (90%)

Rated (4.3/5)