Problem: Provide and show all answers and step by step work to obtain the answer, not skipping any steps. Show all equations, acronyms (ie ETC, ACWP, etc), and if applicable, a description of how you came to the answer.
Problem:

If TCPI = 1.00, BCWP=40, ACWP=60, and BAC = 100, then EAC is most likely?

a) overstated

b) understated

c) accurate

d) not enough information.