Draw the network what is the critical path what is the


1. Schedule the following activities using CPM:

Activity

Time

Pred 1

Pred 2

A

1

-

 

B

4

A

 

C

3

A

 

D

2

B

 

E

5

C

D

F

2

D

 

G

2

F

 

H

3

E

G

a. Draw the network.

b. What is the critical path?

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?

2. The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required:

Activity

Time

Pred 1

Pred 2

Pred 3

A

3

-

 

 

B

2

A

 

 

C

4

A

 

 

D

4

A

 

 

E

6

B

 

 

F

6

C

D

 

G

2

D

F

 

H

3

D

F

 

I

3

E

G

H

a. Draw the network diagram.

b. What is the critical path?

c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten?

d. What is the new critical path and earliest completion time?

02 section 1 STRATEGY, PRODUCTS, AND CAPACITY

8. The following represents a project that should be scheduled using CPM:

Activity

Optimistic

(a)

Likely

(m)

Pessimistic

(b)

Mean

(a+4m+b)/6

Std dev

s= (b-a)/6

Variance

s^2

A

1

3

5

                3.00

         0.67

         0.44

B

1

2

3

                2.00

         0.33

         0.11

C

1

2

3

                2.00

         0.33

         0.11

D

2

3

4

                3.00

         0.33

         0.11

E

3

4

11

                5.00

         1.33

         1.78

F

3

4

5

                4.00

         0.33

         0.11

G

1

4

6

                3.83

         0.83

         0.69

H

2

4

5

                3.83

         0.50

         0.25

a. Draw the network.

b. What is the critical path?

c. What is the expected project completion time?

d. What is the probability of completing this project within 16 days?

9. There is an 82 percent chance the project below can be completed in X weeks or less. What is X?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Draw the network what is the critical path what is the
Reference No:- TGS01087872

Expected delivery within 24 Hours