Draw the network for this project and label the activities


Question: Construction of a building is based on the following CPM network:

1895_Activity.png

a. Draw the network for this project and label the activities.

b. What are the normal project completion time and normal cost?

c. Identify the critical path.

d. How much will it cost to crash the project completion by one day? by two days?

e. What is the minimum time for project completion?