Discuss the primary duties of the termination manager


Problem 1. What is a WBS? Describe it's purpose. Discuss the benefits of using it.

Problem 2. What is a Gantt chart? What is the Critical Path and how is it used?

Problem 3. Create a simple task schedule network (MS Project is not required but preferred). (Minimum of 15 tasks.) The content is up to you. Minimum requirements are as follows: predecessor/successor relationships, duration, task description, start date, end date.

Problem 4. What are the Triple Contraints and why they are important to understand?

Problem 5. Describe the various ways a project may be terminated. Discuss the primary duties of the termination manager?