Discuss the percentage-of-completion method


On March 1, 2012, Chance Company entered into a contract to build an apartment building. It is estimated that the building will cost $2,172,000 and will take 3 years to complete. The contract price was $3,121,000. The following information pertains to the construction period.



2012


2013


2014

Costs to date
$673,320
$1,602,840
$2,014,000
Estimated costs to complete
1,498,680
563,160
-0-
Progress billings to date
855,000
1,853,000
3,121,000
Cash collected to date
810,000
1,707,000

3,009,000

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Discuss the percentage-of-completion method
Reference No:- TGS0691844

Expected delivery within 24 Hours