Determine the unit cost for the month for materials


Question:

During the month, a company with no departmentalization incurred costs of $45,000 for materials, $36,000 for labor, and $22,500 for factory overhead. There were no units in process at the beginning or at the end of the month, and 20,000 units were completed.

Determine the unit cost for the month for materials, labor, and factory overhead.