Current period using the activity-based costing approach


Problem: Cabat Company manufactures two products, Product C and Product D.  The company estimated it would incur $177,910 in manufacturing overhead costs during the current period.  Overhead currently is applied to the products on the basis of direct labor hours.  Data concerning the current period’s operations appear below:

 

Product C

Product D

Estimated volume

3,800 units

3,000 units

Direct Labor hours per unit

1.20 hours

0.80 hour

Direct materials cost per unit

$11.60

$23.70

Direct labor cost per unit

$10.80

$7.20

Required:

1. Compute the predetermined overhead rate, and determine the unit product cost of each product for the current year.

2. The company is considering using an activity-based costing system to compute unit product costs for external financial reports instead of its traditional system based on direct labor hours. The activity-based costing system would use three activity cost pools.  Data relating to these activities for the current period are given below:

Activity Cost Pool

Estimated Overhead Costs

Expected Activity

 

Product C

Product D

Total

Machine setups

$12,190

110

120

230

Purchase Orders

75,240

820

1,160

1,980

General factory

90,480

4,560

2,400

6,960

 

$177,910

 

 

 

Determine the unit product cost of each product for the current period using the activity-based costing approach.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Current period using the activity-based costing approach
Reference No:- TGS01738961

Now Priced at $25 (50% Discount)

Recommended (99%)

Rated (4.3/5)