Contracts for small businesses


James will award six contracts.

- Office supply contract with a cost to be expected at $200,000

- Furniture contract with a cost to be expected at $50,000

- Computer contract with a cost to be expected at $245,000

- The construction contract with a cost expected to be over $2 million

- The IT Services contract with a cost between $2 million and $4 million

- The computer destruction contract with a cost to be expected at $65,000

Should James set-aside any of the contracts for small businesses?

A) Yes, the computer destruction contract because FAR 19.502-2 states that purchases over $3000, but below the simplified acquisition threshold (SAT) of $150,000, must be set-aside for small business which limits the competition to only small businesses.

B) Yes, the computer contract because FAR 19.502-2 states that purchases over the SAT ($150,000) must be set-aside for small business, which limits the competition to only small businesses.

C) Yes, the office supply contract because FAR 19.502-2 states that purchases under $25,000 must be set-aside for small business, which limits the competition to only small businesses.

D) No, because FAR 6.203 states that purchases over $10,000 must be solicited from a single responsible source.

Solution Preview :

Prepared by a verified Expert
Business Law and Ethics: Contracts for small businesses
Reference No:- TGS01755403

Now Priced at $20 (50% Discount)

Recommended (91%)

Rated (4.3/5)