Compute the delivery cycle time for each month


DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations.


Month

1 2 3 4
Throughput time (days) ? ? ? ?
Delivery cycle time (days) ? ? ? ?
Manufacturing cycle efficiency (MCE) ? ? ? ?
Percentage of on-time deliveries 77% 78% 83% 90%
Total sales (units) 10,570 10,400 10,430 10,400

Management would like to know the company's throughput time, manufacturing cycle efficiency, and delivery cycle time. The data to compute these measures have been gathered and appear below:


Average per Month (in days)

1 2 3 4
Move time per unit 0.7
0.3
0.5
0.5
Process time per unit 0.4
0.5
0.5
0.3
Wait time per order before start
of production
9.0
8.0
5.0
4.0
Queue time per unit 3.0
3.0
2.0
1.0
Inspection time per unit 0.3
0.4
0.4
0.6

Requirement 1:
(a) Compute the throughput time for each month. (Round your answers to 1 decimal place.)

1 2 3 4
Total throughput time _________    _________ _________ _________

(b)

Compute the manufacturing cycle efficiency (MCE) for each month. (Round your answers to 1 decimal place. Omit the "%" sign in your response.)


1 2 3 4
Manufacturing cycle efficiency (MCE) _________% _________% _________% _________%

(c) Compute the delivery cycle time for each month. (Round your answers to 1 decimal place.)

1 2 3 4
Total delivery cycle time _________ _________ _________ _________

Requirement 2:
Refer to the move time, process time, and so forth, given above for month 4.
(a)

Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE. (Round your answers to 1 decimal place. Omit the "%" sign in your response.)

Total throughput time                      _________
Manufacturing cycle efficiency (MCE) _________%
(b)

Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE. (Round your answers to 1 decimal place. Omit the "%" sign in your response.)

Total throughput time        _________
Manufacturing cycle efficiency (MCE)     _________%

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Compute the delivery cycle time for each month