Communication system for commercial planes


Problem: The R&D dept. is planning to bid on a large project for the development of a new communication system for commercial planes. 

The accompanying table shows the activities, time & sequence required:

Activity

Immediate predecessor

Time (weeks)

A

---

3

B

A

2

C

A

4

D

A

4

E

B

6

F

C,D

6

G

D,F

2

H

D

3

I

E,G,H

3


1) What is the critical path?

2) Suppose you want to shorten the completion time as much as possible, & you have the option of shortening any or all of B,C,D, and G each one week.  Which would you shorten?

3) What is the new critical path & earliest completion time?