Calculate the expected duration of each activity


Task: You will be provided a list of the activities of a project with completion time estimate for each activity. You will be asked to answer the following questions.

Question 1: Calculate the expected duration of each activity. Also, calculate the expected duration of each path.

Question 2: Calculate the variance of each activity and variance of each path. Also, calculate the standard deviation of each activity and the standard deviation of each path.

Question 3: Identify the critical path(s) (based on the expected durations).

Question 4: What is the probability that the project can be completed within 49 weeks? What is the probability that the project will NOT be completed within 49 weeks?

Question 5: What is the probability that the project will require 47 weeks or more? What is the probability that the project will NOT require more than 47 weeks?

Question 6: What is the probability that the project will be completed between 45 and 50 weeks?

PLEASE SEE THE DATA.

ACTIVITY Predecessor  Time Estimates (Minutes)


A M B
1 - 8 8 8
2 1 11 12 13
3 2 9 10 12
4 3 5 7 10
5 1 5 6 7
6 5 14 18 26
7 6 8 10 14
8 5 13 13 13
9 8 10.5 13 15.5
10 1 10 12 14
11 10 7 10 12
12 11 10 11 12
13 13 6 6 6

Solution Preview :

Prepared by a verified Expert
Other Management: Calculate the expected duration of each activity
Reference No:- TGS01768583

Now Priced at $25 (50% Discount)

Recommended (91%)

Rated (4.3/5)