Average time to complete a project


A new integrated computer system is to be installed worldwide for a major corporation. Bids on this project are being solictied, and the contract will be awarded to one of the bidders. As a part of the proposal for this project, bidders must specify how long the project will take. There will be a significant penalty for finishing late. One potential contractor determines the average time to complete a project of this type is 40 weeks with a standard deviation of 5 weeks. The time required to complete this project is assumed to be normally distributed. If the bidder wishes to set the due date in the proposal so that there is only a 5% chance of being late (and consequently only a 5% chance of having to pay a penalty), what due date should be set?

(1) If the due date of this project is set at 40 weeks, what is the probability that the project will not be finished on schedule?

(2) If the due date of this project is set at 43 weeks, what is the probability that the contractor will not finish on time?

Request for Solution File

Ask an Expert for Answer!!
Basic Statistics: Average time to complete a project
Reference No:- TGS0721675

Expected delivery within 24 Hours