A project team has started gathering information necessary


A project team has started gathering information necessary to develop a project network-predecessor activities.

The results of their meeting are found in the following table:

Activity

Description

Predecessor

Duration

1

Meeting

-


2

Design

-

6

3

Procure prototype parts

1, 2

3

4

Fabricate parts

2

5

5

Assemble prototype

3,4

3

6

Laboratory test

5

2

7

Field test

6

4

8

Adjust design

7

2

9

Order stock components

8

3

10

Order custom components

8

1

11

Assemble test production unit

9,10

5

12

Test unit

11

2

13

Document results

12

2

a) Develop a network

b) Find the slack time on activity if there any in the network

c) Find the critical path

Request for Solution File

Ask an Expert for Answer!!
Operation Management: A project team has started gathering information necessary
Reference No:- TGS02718444

Expected delivery within 24 Hours