A project has an expected completion time of 40 weeks and a standard deviation of 5 weeks. It is assumed that the project completion time is normally distributed.

  • What is the probability of finishing the project in 50 weeks or less?
  • What is the probability of finishing the project in 38 weeks or less?
  • The due date for the project is set so that there is a 90% chance that the project will be finished by this date.What is the date?